Here’s the weekly progress report from WM Jordan:

  • WMJ punched the existing building. Trade partners are working on the list of items.
  • Matchless Concrete continued placing sidewalks.
  • Raby Construction spread stone and prepped parking area for asphalt. Raby also removed the old asphalt and prepped the ETO lot for paving.
  • Willow Tree began installing the irrigation system.
  • Upstate Commercial installed base, LVP, and delivered the wood flooring for the platform.
  • Johnson Electric prepared for final inspections.
  • Thomas Mechanical started up AH-3’s and prepared for finals.
  • AFD Construction installed remaining trim at platform.
  • BMG Solutions continued low voltage installation.
 

Pray for the final stages of the construction work, landscaping, and paving to go well and finish in a timely manner. Pray for those involved, and thank God for all He has done for us!

WEBC - setting out new kitchen equipment
New South - Installation of toilet partitions
Upstate Commercial Installation of LVP and walk-off mat