We’re entering the month of November and we are so excited about how God is providing for our church in so many ways. Yes, we will have a wonderful new building to worship and serve our community in – but we also have so many of our church members stepping into new volunteer roles in order to make our move and our life in the new building a wonderful experience for all. Let’s thank God for how He is moving in our midst!
Here’s the progress report from WM Jordan:
- AFD Construction laid the ceiling tiles throughout, insulated and hung drywall for the divider wall, and began framing the Sanctuary platform.
- Johnson Electric installed the projector screen and wrapped up their device trim-out.
- Upstate Commercial began installing floor finishes throughout.
- Raby Construction completed fine grading the site, installed the retaining wall, and placed the curb and gutter for the parking area.
- Matchless Concrete placed half of the Arlington Sidewalk and also the courtyard concrete.
- Woodco installed the countertop for the Entry 109 millwork.